A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?
A .  Strong
B .  Weak
C .  Managed
D .  Balanced

Answer: D