A large portion of a projects budget is typically expended on the processes in which Process Group?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

A large portion of a projects budget is typically expended on the processes in which Process Group?
A .  Executing
B .  Planning
C .  Monitoring and Controlling
D .  Closing

Answer: B