A project is running behind schedule. To meet the delivery timelines, the project manager decides to give part of the work to another organization for quicker delivery and to allow the project team to focus on the remaining tasks.

Posted by: Pdfprep Category: PK0-004 Tags: , ,

A project is running behind schedule. To meet the delivery timelines, the project manager decides to give part of the work to another organization for quicker delivery and to allow the project team to focus on the remaining tasks.

This is an example of:
A . crashing.
B . outsourcing.
C . task reassignment.
D . relocation.

Answer: C