A report scheduled to run every 15 mins. but takes 17 mins. to complete is in danger of being_____.

A report scheduled to run every 15 mins. but takes 17 mins. to complete is in danger of being_____.
A . skipped or deferred
B . automatically accelerated
C . deleted
D . all of the above

Answer: A