According to PRINCE2, Project Board members would NOT be involved in which of the following?

According to PRINCE2, Project Board members would NOT be involved in which of the following?
A . Confirming project tolerances with corporate or programme management
B . Authorizing the start of the project
C . Running of the project on a day-to-day basis
D . Communications between the project management team and stakeholders external to that team

Answer: C