According to PRINCE2, which of the following are the aspects of project performance to be managed?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

According to PRINCE2, which of the following are the aspects of project performance to be managed?
A . Processes, themes, principles
B . Time, cost, quality, people
C . Time, cost, quality
D . Time, cost, quality, scope, benefits, risk

Answer: D