Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?
A .  Estimate Costs
B .  Control Costs
C .  Plan Cost Management
D .  Determine Budget

Answer: D