Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: October 22, 2020 Pdfprep2020-10-22T22:12:02+00:00 An input to the Manage Project Team process is:A . Work performance reports.B . Change requests.C . Activity resource requirements.D . Enterprise environmental factors. View Answer Answer: A Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.