An input to the Perform Integrated Change Control process is:

Posted by: Pdfprep Category: PMI-001 Tags: , ,

An input to the Perform Integrated Change Control process is:
A .  expert judgment
B .  seller proposals
C .  the project charter
D .  the project management plan

Answer: D