Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: November 15, 2020 Pdfprep2020-11-15T16:13:21+00:00 An output of Control Schedule is:A . Aproject schedule network diagramB . Aschedule managementplanC . Schedule dataD . Schedule forecasts View Answer Answer: D Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.