Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: November 17, 2020 Pdfprep2020-11-17T09:05:25+00:00 An output of the Develop Project Team process is:A . change requestsB . team performance assessmentsC . project staff assignmentsD . project documents updates View Answer Answer: B Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.