As an active project stakeholder, to which meeting should the IT director be invited?

A scrum master is part of a project team using technologies overseen by the IT department. The IT director oversees several company initiatives and is unfamiliar with the details of each one.

As an active project stakeholder, to which meeting should the IT director be invited?
A . Planning
B . Daily scrum
C . Sprint demo
D . Retrospective

Answer: D