Based on an average of 8 software projects at a current cost of $50,000 each, how many years will it take to see a positive ROI?

Posted by: Pdfprep Category: CAS-001 Tags: , ,

To support a software security initiative business case, a project manager needs to provide a cost benefit analysis. The project manager has asked the security consultant to perform a return on investment study. It has been estimated that by spending $300,000 on the software security initiative, a 30% savings in cost will be realized for each project.

Based on an average of 8 software projects at a current cost of $50,000 each, how many years will it take to see a positive ROI?
A . Nearly four years
B . Nearly six years
C . Within the first year
D . Nearly three years

Answer: D