Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?
A .  Perform Quality Assurance
B .  Direct and Manage Project Work
C .  Monitor and Control Project Work
D .  Perform Integrated Change Control

Answer: D