Due to the large number of requirements, which of the following methods should the team use?

A project team needs to maintain the traceability of requirements for a software system.

Due to the large number of requirements, which of the following methods should the team use?
A . Use a requirements management tool
B . Create a requirements mode
C . Maintain the requirements manually
D . Develop a database management system

Answer: A

Explanation:

Requirements traceability is documented and maintained in accordance with the methods identified by the business analysis approach. Requirements management tools can provide significant benefits when there is a need to trace a large number of requirements that may be deemed unmanageable with manual approaches.