During a work package the Team manager needs to keep the project manager informed, which management product is used for this?

During a work package the Team manager needs to keep the project manager informed, which management product is used for this?
A . Highlight report
B . Checkpoint Report
C . Issue Report
D . End Stage Report

Answer: B