During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

Posted by: Pdfprep Category: PRF Tags: , ,

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?
A .  End Stage Report
B .  Team Plan
C .  Work Package
D .  Project Plan

Answer: D