During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?
A .  Monitor and Control Project Work
B .  Perform Quality Assurance
C .  Close Project or Phase
D .  Control Scope

Answer: C