Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: November 1, 2020 Pdfprep2020-11-01T14:18:09+00:00 During which process does the project team receive bids and proposals?A . Conduct ProcurementsB . Plan ProcurementsC . Estimate CostsD . Control Budget View Answer Answer: A Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.