How should the ScrumMaster respond?

Posted by: Pdfprep Category: PMI-200 Tags: , ,

During iteration planning, the team is discussing the design for a user story. A team member states that a design document should be started since the system is complex in nature. Another team member responds that in Agile there is no documentation.

How should the ScrumMaster respond?
A . Agree that documentation should be avoided, since it slows the progress of the team.
B . Explain that interactions are valued over documentation, but documentation is not forbidden.
C . Ask the manager if the technical processes mandate that designs be documented.
D . Ask the Product Owner if it is acceptable for the resources to spend time on documentation.

Answer: B