How should you address this?

Posted by: Pdfprep Category: ASM Tags: , ,

Your team uses Story Points to estimate User stories.

Halfway through a Sprint, you are not seeing the progress you expected. The Team feels some Stories are not estimated correctly, when compared to other Stories.

How should you address this?
A . Complete incomplete Stories
B . Increase or re-estimate Velocity
C . Re-estimate all small Stories
D . Switch to using Ideal days

Answer: A