Identify the missing word in the following sentence. The [?] theme defines that the Project Board is responsible for the overall direction and management of the project,

Posted by: Pdfprep Category: PRF Tags: , ,

Identify the missing word in the following sentence. The [?] theme defines that the Project Board is responsible for the overall direction and management of the project,
A .  Progress
B .  Plans
C .  Organization
D .  Business Case

Answer: C

Leave a Reply

Your email address will not be published.