Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.

Posted by: Pdfprep Category: PRF Tags: , ,

Identify the missing words in the following sentence.During the Initiating a Project process the [?] before a project is authorized.
A .  minimum necessary is done to decide if a project is worthwhile
B .  aim is to establish sound foundations to achieve a successful project
C .  Project Brief is assembled and approved
D .  project approach appropriate for delivering a project is selected

Answer: B