Identify the missing word(s) in the following sentence… PRINCE2 recommends three [ ? ] to reflect the needs of the different levels of management involved in a project.

Identify the missing word(s) in the following sentence… PRINCE2 recommends three [ ? ] to reflect the needs of the different levels of management involved in a project.
A . Levels of issue
B . Stakeholders
C . Levels of plan
D . Types of risk responses

Answer: C