PdfPrep.com

If an IS auditor observes that individual modules of a system perform correctly in development project tests, the auditor should inform management of the positive results and recommend further:

If an IS auditor observes that individual modules of a system perform correctly in development project tests, the auditor should inform management of the positive results and recommend further:
A . Documentation development
B . Comprehensive integration testing
C . Full unit testing
D . Full regression testing

Answer: B

Explanation:

If an IS auditor observes individual modules of a system perform correctly in development project tests, the auditor should inform management of the positive results and recommend further comprehensive integration testing.

Exit mobile version