If, for whatever reason, the business justification disappears once the project is underway, what does PRINCE2 suggest should happen?

If, for whatever reason, the business justification disappears once the project is underway, what does PRINCE2 suggest should happen?
A . The project should continue until the next end stage assessment
B . A benefits review should be undertaken
C . The project should be stopped or changed
D . An exception assessment should be held to approve an Exception Plan to recover from the situation

Answer: C