If the Project Board wish to ensure the Communications Management Strategy covers all the stakeholders requirements for the next stage, which project management team role may they appoint to check this for them?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

If the Project Board wish to ensure the Communications Management Strategy covers all the stakeholders requirements for the next stage, which project management team role may they appoint to check this for them?
A . Project Assurance
B . Project Support
C . Project Manager
D . Quality Assurance

Answer: A