If the wait time for the step remain at 5 days, what day of the designated 5 days of wait time would the prospect be on when the program is restarted?

Posted by: Pdfprep Category: PDX-101 Tags: , ,

A project is on day 3 of a step with a designated wait time of 5 days. The engagement studio program is then paused for 1 day and restarted.

If the wait time for the step remain at 5 days, what day of the designated 5 days of wait time would the prospect be on when the program is restarted?
A . Day 4
B . Day 3
C . Day 0
D . Day 5

Answer: A