If you use floats to limit dispatching in capacity planning, what type of time element can be reduced by strategy settings while dispatching?

Posted by: Pdfprep Category: C_TS422_2020 Tags: , ,

If you use floats to limit dispatching in capacity planning, what type of time element can be reduced by strategy settings while dispatching?
A . Queue time
B . Production time
C . Minimum wait time
D . Goods receipt processing time

Answer: A