In respect of the project’s organization structure, one of the seven principles of PRINCE2 is that every project must have which one of the following?

In respect of the project’s organization structure, one of the seven principles of PRINCE2 is that every project must have which one of the following?
A . Defined and agreed roles and responsibilities with an organization structure that engages the business, user and supplier primary stakeholder interests
B . People allocated to clearly defined management jobs, assigned to them on a one-to-one basis
C . As many stakeholders as possible from the customer environment involved in key decision-making throughout the project life cycle
D . Stakeholders who are responsible, accountable, consulted and informed throughout every stage of the project

Answer: A