In respect to the attributes of the requirements engineer, which of the following statements implies the greatest risk for the requirements engineering?

Posted by: Pdfprep Category: IREB Tags: , ,

You are project manager for a system that your company is creating for the military in the field of logistics. A requirements engineer has been assigned to your project but does not have all the desirable skills for this role.

In respect to the attributes of the requirements engineer, which of the following statements implies the greatest risk for the requirements engineering? (1 Point)
A . The requirements engineer is not familiar with the military ranks and so cannot deal adequately with the hierarchical sensitivities.
B . The requirements engineer does not have detailed knowledge of the military norms and standards that should be applied to the system.
C . The requirements engineer has no solid project management training.
D . The requirements engineer is introverted and has no knowledge of requirements elicitation and documentation.

Answer: D