Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
A .  Plan Cost Management
B .  Plan Scope Management
C .  Plan Stakeholder Management
D .  Plan Schedule Management

Answer: C