Please refer to A.9 in the PRINCE2 Manual. (A summary of issues and risks would be included but the End Stage Report is not used to ‘capture and maintain’ information regarding issues and risks. This would be in the respective Registers.)

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

Please refer to A.9 in the PRINCE2 Manual. (A summary of issues and risks would be included but the End Stage Report is not used to ‘capture and maintain’ information regarding issues and risks. This would be in the respective Registers.)

A. Capture and maintain information regarding issues and risks

B. Document the project’s acceptance criteria

C. Escalate a stage-level tolerance threat to the Project Board

D. Give a summary of progress to date

Answer: D