PdfPrep.com

Please refer to section 10.3.2.1 in the PRINCE2 Manual. (Exception Plans are only produced if requested by the Project Board. Team Plans and the use of seperate people as Team Managers are optional in PRINCE2)

Please refer to section 10.3.2.1 in the PRINCE2 Manual. (Exception Plans are only produced if requested by the Project Board. Team Plans and the use of seperate people as Team Managers are optional in PRINCE2)
A . Use of Team Managers
B . Use of management stages
C . Use of Exception Plans
D . Use of Team Plans

Answer: B

Exit mobile version