Scope, schedule, and cost parameters are integrated in the:

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Scope, schedule, and cost parameters are integrated in the:
A .  Performance measurement baseline.
B .  Analysis of project forecasts,
C .  Summary of changes approved in a period,
D .  Analysis of past performance.

Answer: A