Sprint 6: 10 pontos The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?

Posted by: Pdfprep Category: CSM-001 Tags: , ,

You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information: Sprint 1: 10 pontos Sprint 2: 11 pontos Sprint 3: 15 pontos Sprint 4: 14 pontos Sprint 5: 15 pontos

Sprint 6: 10 pontos The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?
A .  6
B .  5
C .  4
D .  3

Answer: B