Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
A .  Earned value management.
B .  Enterprise environmental factors.
C .  Organizational process assets.
D .  Work performance information.

Answer: D