PdfPrep.com

The creation of an Exception Plan often follows which of the following situations?

The creation of an Exception Plan often follows which of the following situations?
A . A time or cost slippage occurring during a management stage
B . An Exception Report being submitted to the Project Board in the case of a management stage being forecast to exceed its tolerance
C . A Stage Plan updated due to an urgent corrective action being taken by the Project Manager
D . A newly identified risk being captured and documented in the Risk Register

Answer: B

Exit mobile version