The critical path for any project is the path that exhibits which of the following characteristics?

The critical path for any project is the path that exhibits which of the following characteristics?
A . Has the longest duration in time.
B . Costs the most money.
C . Requires the largest amount of labor
D . Is deemed most important to the project.

Answer: A