The following are the three categories of risk tolerance associated with the stakeholders except for which one?

Posted by: Pdfprep Category: CCBA Tags: , ,

You are the business analyst for your organization and working with the stakeholders to prioritize the requirements. The stakeholders are concerned about the financial impact of the requirements should some of them fail during the implementation. You would like to rank the risk tolerance of the stakeholders based on their comments about the solution and the requirements.

The following are the three categories of risk tolerance associated with the stakeholders except for which one?
A . Neutrality
B . Mitigation
C . Risk-seeking
D . Risk-aversion

Answer: B

Explanation:

Mitigation is a risk response that seeks to lower the risk’s probability and/or impact. It is not one of the three categories of risk tolerance.

Leave a Reply

Your email address will not be published.