The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
A .  Project Communications Management
B .  Project Integration Management
C .  Project Risk Management
D .  Project Scope Management

Answer: B