The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?

The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?
A . Scope, People & Resources, Benefit
B . Scope, Risk, Product
C . Risk, Benefit, Product
D . Scope, Risk, Benefit

Answer: D