The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

Posted by: Pdfprep Category: PMI-001 Tags: , ,

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:
A .  Work packages.
B .  Accepted deliverables.
C .  The WBS dictionary.
D .  The scope baseline.

Answer: A