The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

Posted by: Pdfprep Category: PMI-001 Tags: , ,

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:
A .  Define Activities.
B .  Sequence Activities.
C .  Define Scope.
D .  Control Schedule.

Answer: A