There should be at least two management stages in a PRINCE2 project. Which of the following options describes those stages?

Posted by: Pdfprep Category: PRINCE2 Tags: , ,

There should be at least two management stages in a PRINCE2 project. Which of the following options describes those stages?
A . Initiation as the first stage, the remainder of the project as the second stage
B . Initiation as the first stage, closure activities as the second stage
C . Procurement as the first stage, design and implementation as the second stage
D . Pre-project work as the first stage, initiation as the second stage

Answer: A