This should be updated by an it_pps_admin, so that the stakeholder list will automatically populate when a user creates a demand or project.
A . Project form.
B . Stakeholder registry.
C . Demand form.
D . Application registry.
Answer: B
This should be updated by an it_pps_admin, so that the stakeholder list will automatically populate when a user creates a demand or project.
A . Project form.
B . Stakeholder registry.
C . Demand form.
D . Application registry.
Answer: B