Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

Posted by: Pdfprep Category: PMI-001 Tags: , ,

Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?
A .  Close Project or Phase
B .  Conduct Procurements
C .  Control Procurements
D .  Close Procurements

Answer: D