PdfPrep.com

Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?

A team member has reported Task 3 will be completed ahead of schedule.

Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?
A . 8 days
B . 10 days
C . 11 days
D . 12 days

Answer: D

Exit mobile version