What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.

Posted by: Pdfprep Category: C_TS422_2020 Tags: , ,

What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.
A . Alternative resources are fully occupied.
B . The Change Planning Direct on indicator is set.
C . The work center has several individual capacities.
D . The planning strategy is infinite.

Answer: C,D