What is the best first step the business analyst should take regarding this risk?

Posted by: Pdfprep Category: PMI-200 Tags: , ,

A business analyst has identified a new risk in an Agile project.

What is the best first step the business analyst should take regarding this risk?
A . Call a meeting with the project manager and senior management to determine how the risk will be managed.
B . Email the project manager and add it to the risk register so that it is discussed during the next daily standup.
C . Add the risk in a clearly visible location and ensure it is discussed after the next daily stand up.
D . Call an immediate meeting with all team members to discuss the newly identified risk.

Answer: C